1100MW Paul (G9)

1100MW Paul is a 1,100.0 MW gas interconnection project in Lewis, Washington with a current status of withdrawn. It is proposed to connect at Paul 500 kV Substation.

1,100.0 MWCapacity
WithdrawnStatus
WAMarket
GasTechnology

Project facts

Canonical name1100MW Paul
Queue IDG9
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyGas
Capacity1,100.0 MW
StateWashington
CountyLewis
Point of interconnectionPaul 500 kV Substation
Requested (queue) date2000-08-28
Proposed in-service date2004-07-01
Operational date
Withdrawn date
DeveloperCogentrix Energy, Inc.
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.