1200 MW non-controllable ETU - N to S flow only (1230)
1200 MW non-controllable ETU - N to S flow only is a 1,200.0 MW generation interconnection project in Somerset/Aroostook, Maine with a current status of withdrawn. It is proposed to connect at The Point of Interconnection will be a new station about 30 miles from Orrington that taps the existing segment 3023 between Orrington and Albion Rd. Hammond, ME to Pittsfield ME (see map).
1,200.0 MWCapacity
WithdrawnStatus
MEMarket
GenerationTechnology
Project facts
| Canonical name | 1200 MW non-controllable ETU - N to S flow only |
|---|---|
| Queue ID | 1230 |
| Status | withdrawn |
| Source status | W |
| Market | ME |
| Technology | Generation |
| Capacity | 1,200.0 MW |
| State | Maine |
| County | Somerset/Aroostook |
| Point of interconnection | The Point of Interconnection will be a new station about 30 miles from Orrington that taps the existing segment 3023 between Orrington and Albion Rd. Hammond, ME to Pittsfield ME (see map) |
| Requested (queue) date | 2022-03-04 |
| Proposed in-service date | 2027-12-01 |
| Operational date | — |
| Withdrawn date | 2025-10-11 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata