150 kV HVDC Tie - Import Only (498)

150 kV HVDC Tie - Import Only is a 400.0 MW generation interconnection project in Colchester, Vermont with a current status of withdrawn. It is proposed to connect at NYPA 230/115 kV substation to VELCO 345 kV New Haven Substation.

400.0 MWCapacity
WithdrawnStatus
VTMarket
GenerationTechnology

Project facts

Canonical name150 kV HVDC Tie - Import Only
Queue ID498
Statuswithdrawn
Source statusW
MarketVT
TechnologyGeneration
Capacity400.0 MW
StateVermont
CountyColchester
Point of interconnectionNYPA 230/115 kV substation to VELCO 345 kV New Haven Substation
Requested (queue) date2015-02-16
Proposed in-service date2020-12-31
Operational date
Withdrawn date2018-02-02
Developer
Utility / transmission ownerISO-NE

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.