345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND (GEN-2021-008)

345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND is a 200.0 MW solar interconnection project in McKenzie, North Dakota with a current status of withdrawn. It is proposed to connect at 345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND.

200.0 MWCapacity
WithdrawnStatus
NDMarket
SolarTechnology

Project facts

Canonical name345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND
Queue IDGEN-2021-008
Statuswithdrawn
Source statusWITHDRAWN
MarketND
TechnologySolar
Capacity200.0 MW
StateNorth Dakota
CountyMcKenzie
Point of interconnection345kV Bus at BEPC Patent Gate Substation, McKenzie County, ND
Requested (queue) date2021-05-10
Proposed in-service date2030-10-19
Operational date
Withdrawn date2026-01-07
Developer
Utility / transmission ownerBEPC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata