69kV ring bus interconnecting to Sedalia and Nichols Street (GEN-2018-018)

69kV ring bus interconnecting to Sedalia and Nichols Street is a 57.0 MW solar interconnection project in Springfield, Missouri with a current status of withdrawn. It is proposed to connect at 69kV ring bus interconnecting to Sedalia and Nichols Street.

57.0 MWCapacity
WithdrawnStatus
MOMarket
SolarTechnology

Project facts

Canonical name69kV ring bus interconnecting to Sedalia and Nichols Street
Queue IDGEN-2018-018
Statuswithdrawn
Source statusWITHDRAWN
MarketMO
TechnologySolar
Capacity57.0 MW
StateMissouri
CountySpringfield
Point of interconnection69kV ring bus interconnecting to Sedalia and Nichols Street
Requested (queue) date2018-05-08
Proposed in-service date
Operational date
Withdrawn date2018-06-04
Developer
Utility / transmission ownerSPP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.