AGATE BESS (68366_AGAT)

AGATE BESS is a 170.0 MW battery interconnection project in Kitsap, Washington with a current status of active.

170.0 MWCapacity
ActiveStatus
PSEIMarket
BatteryTechnology

Project facts

Canonical nameAGATE BESS
Queue ID68366_AGAT
Statusactive
Source status(L) Regulatory approvals pending. Not under construction
MarketPSEI
TechnologyBattery
Capacity170.0 MW
StateWashington
CountyKitsap
Point of interconnection—
Requested (queue) date—
Proposed in-service date2029-02-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerBrightNight Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-02proposed_online_date2027-12-012029-02-01medium
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata