Alabama Power IC-104 (IC-104)

Alabama Power IC-104 is a 630.0 MW gas interconnection project in Lee County, Alabama with a current status of withdrawn. It is proposed to connect at Fortson 500 kV.

630.0 MWCapacity
WithdrawnStatus
ALMarket
GasTechnology

Project facts

Canonical nameAlabama Power IC-104
Queue IDIC-104
Statuswithdrawn
Source status
MarketAL
TechnologyGas
Capacity630.0 MW
StateAlabama
CountyLee County
Point of interconnectionFortson 500 kV
Requested (queue) date
Proposed in-service date
Operational date
Withdrawn date2003-03-05
Developer
Utility / transmission ownerAlabama Power Co

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata