Alabama Power IC-1114 (IC-1114)

Alabama Power IC-1114 is a 951.0 MW gas interconnection project in Autauga County, Alabama with a current status of operational. It is proposed to connect at Billingsley SS Substation 500 kV Bus.

951.0 MWCapacity
OperationalStatus
ALMarket
GasTechnology

Project facts

Canonical nameAlabama Power IC-1114
Queue IDIC-1114
Statusoperational
Source statusCommercial Operation
MarketAL
TechnologyGas
Capacity951.0 MW
StateAlabama
CountyAutauga County
Point of interconnectionBillingsley SS Substation 500 kV Bus
Requested (queue) date2023-01-10
Proposed in-service date2024-07-01
Operational date2024-07-01
Withdrawn date
Developer
Utility / transmission ownerAlabama Power Co

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata