Alabama Power IC-415 (IC-415)

Alabama Power IC-415 is a 72.0 MW solar interconnection project in Chambers County, Alabama with a current status of operational. It is proposed to connect at North Auburn - Roanoke 115 kV Line.

72.0 MWCapacity
OperationalStatus
ALMarket
SolarTechnology

Project facts

Canonical nameAlabama Power IC-415
Queue IDIC-415
Statusoperational
Source statusCommercial Operation
MarketAL
TechnologySolar
Capacity72.0 MW
StateAlabama
CountyChambers County
Point of interconnectionNorth Auburn - Roanoke 115 kV Line
Requested (queue) date2015-07-16
Proposed in-service date2017-08-31
Operational date2017-08-31
Withdrawn date
Developer
Utility / transmission ownerAlabama Power Co

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata