Alabama Power IC-666 is a 707.0 MW gas interconnection project in Jefferson County, Alabama with a current status of operational. It is proposed to connect at Miller SP 230 kV Bus.
707.0 MWCapacity
OperationalStatus
ALMarket
GasTechnology
Project facts
| Canonical name | Alabama Power IC-666 |
|---|---|
| Queue ID | IC-666 |
| Status | operational |
| Source status | Commercial Operation |
| Market | AL |
| Technology | Gas |
| Capacity | 707.0 MW |
| State | Alabama |
| County | Jefferson County |
| Point of interconnection | Miller SP 230 kV Bus |
| Requested (queue) date | 2018-01-02 |
| Proposed in-service date | 2019-06-01 |
| Operational date | 2019-06-01 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Alabama Power Co |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata