Alabama Power IC-806 (IC-806)

Alabama Power IC-806 is a 685.0 MW gas interconnection project in Mobile County, Alabama with a current status of operational. It is proposed to connect at Ellicott TS Substation 230 kV Bus.

685.0 MWCapacity
OperationalStatus
ALMarket
GasTechnology

Project facts

Canonical nameAlabama Power IC-806
Queue IDIC-806
Statusoperational
Source statusCommercial Operation
MarketAL
TechnologyGas
Capacity685.0 MW
StateAlabama
CountyMobile County
Point of interconnectionEllicott TS Substation 230 kV Bus
Requested (queue) date2019-09-26
Proposed in-service date2022-12-14
Operational date2022-12-14
Withdrawn date
Developer
Utility / transmission ownerAlabama Power Co

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata