Altoona- NE Parson 138kV (GEN-2017-131)

Altoona- NE Parson 138kV is a 29.6 MW battery interconnection project in Wilson, Kansas with a current status of withdrawn. It is proposed to connect at Altoona- NE Parson 138kV.

29.6 MWCapacity
WithdrawnStatus
KSMarket
BatteryTechnology

Project facts

Canonical nameAltoona- NE Parson 138kV
Queue IDGEN-2017-131
Statuswithdrawn
Source statusTERMINATED
MarketKS
TechnologyBattery
Capacity29.6 MW
StateKansas
CountyWilson
Point of interconnectionAltoona- NE Parson 138kV
Requested (queue) date2017-11-22
Proposed in-service date2026-02-01
Operational date
Withdrawn date2025-06-09
Developer
Utility / transmission ownerWERE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.