Anadarko 138kV (GEN-2007-052)

Anadarko 138kV is a 150.0 MW gas interconnection project in Caddo County, Oklahoma with a current status of operational. It is proposed to connect at Anadarko 138kV.

150.0 MWCapacity
OperationalStatus
OKMarket
GasTechnology

Project facts

Canonical nameAnadarko 138kV
Queue IDGEN-2007-052
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketOK
TechnologyGas
Capacity150.0 MW
StateOklahoma
CountyCaddo County
Point of interconnectionAnadarko 138kV
Requested (queue) date2007-11-09
Proposed in-service date
Operational date2009-05-01
Withdrawn date
Developer
Utility / transmission ownerWFEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata