Archie 161kV (GEN-2010-022)

Archie 161kV is a 75.0 MW wind interconnection project in Cass County, Missouri with a current status of withdrawn. It is proposed to connect at Archie 161kV.

75.0 MWCapacity
WithdrawnStatus
MOMarket
WindTechnology

Project facts

Canonical nameArchie 161kV
Queue IDGEN-2010-022
Statuswithdrawn
Source statusWITHDRAWN
MarketMO
TechnologyWind
Capacity75.0 MW
StateMissouri
CountyCass County
Point of interconnectionArchie 161kV
Requested (queue) date2010-03-31
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerMIPU

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.