Arco Wind, LLC (580)

Arco Wind, LLC is a 263.0 MW solar+battery interconnection project in Bingham;#bonneville, Idaho with a current status of withdrawn. It is proposed to connect at Goshen to Jefferson 161kV Line.

263.0 MWCapacity
WithdrawnStatus
IDMarket
Solar+BatteryTechnology

Project facts

Canonical nameArco Wind, LLC
Queue ID580
Statuswithdrawn
Source statusWithdrawn
MarketID
TechnologySolar+Battery
Capacity263.0 MW
StateIdaho
CountyBingham;#bonneville
Point of interconnectionGoshen to Jefferson 161kV Line
Requested (queue) date2020-05-18
Proposed in-service date
Operational date
Withdrawn date
DeveloperArco Wind, LLC
Utility / transmission ownerIdaho Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata