Argenta - Tompkins 345kV Line Tap (J936)

Argenta - Tompkins 345kV Line Tap is a 507.0 MW gas interconnection project in Calhoun County, Michigan with a current status of withdrawn. It is proposed to connect at Argenta - Tompkins 345kV Line Tap.

507.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameArgenta - Tompkins 345kV Line Tap
Queue IDJ936
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity507.0 MW
StateMichigan
CountyCalhoun County
Point of interconnectionArgenta - Tompkins 345kV Line Tap
Requested (queue) date2017-06-16
Proposed in-service date2020-05-01
Operational date2020-05-01
Withdrawn date2019-01-09
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.