Arthur Kill Energy Storage 1 (0827)

Arthur Kill Energy Storage 1 is a 15.0 MW battery interconnection project in Richmond, New York with a current status of active. It is proposed to connect at Fresh Kills 13.8kV.

15.0 MWCapacity
ActiveStatus
JMarket
BatteryTechnology

Project facts

Canonical nameArthur Kill Energy Storage 1
Queue ID0827
Statusactive
Source status12
MarketJ
TechnologyBattery
Capacity15.0 MW
StateNew York
CountyRichmond
Point of interconnectionFresh Kills 13.8kV
Requested (queue) date2019-04-22
Proposed in-service date
Operational date
Withdrawn date
DeveloperLighthouse Arthur Kill II, LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata