ASGI-2013-002 (ASGI-2013-002)

ASGI-2013-002 is a 18.4 MW wind interconnection project in Quay County, New Mexico with a current status of operational.

18.4 MWCapacity
OperationalStatus
NMMarket
WindTechnology

Project facts

Canonical nameASGI-2013-002
Queue IDASGI-2013-002
Statusoperational
Source status—
MarketNM
TechnologyWind
Capacity18.4 MW
StateNew Mexico
CountyQuay County
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2014-12-31
Withdrawn date—
Developer—
Utility / transmission ownerSPP

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata