Ault-Laramie River Station 345 Line (GI-TC-2024-16)
Ault-Laramie River Station 345 Line is a 400.0 MW wind interconnection project in Laramie County, Wyoming with a current status of active. It is proposed to connect at Ault-Laramie River Station 345 Line.
400.0 MWCapacity
ActiveStatus
WYMarket
WindTechnology
Project facts
| Canonical name | Ault-Laramie River Station 345 Line |
|---|---|
| Queue ID | GI-TC-2024-16 |
| Status | active |
| Source status | IA FULLY EXECUTED/ON SUSPENSION |
| Market | WY |
| Technology | Wind |
| Capacity | 400.0 MW |
| State | Wyoming |
| County | Laramie County |
| Point of interconnection | Ault-Laramie River Station 345 Line |
| Requested (queue) date | 2023-05-16 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | TSGT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata