Ault LRS 345 Line (GI-CS-2025-04)

Ault LRS 345 Line is a 330.0 MW wind interconnection project in Laramie County,, Wyoming with a current status of operational. It is proposed to connect at Ault LRS 345 Line.

330.0 MWCapacity
OperationalStatus
WYMarket
WindTechnology

Project facts

Canonical nameAult LRS 345 Line
Queue IDGI-CS-2025-04
Statusoperational
Source statusDISIS STAGE
MarketWY
TechnologyWind
Capacity330.0 MW
StateWyoming
CountyLaramie County,
Point of interconnectionAult LRS 345 Line
Requested (queue) date2025-09-17
Proposed in-service date
Operational date2029-11-30
Withdrawn date
Developer
Utility / transmission ownerTSGT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; tristate-oasis. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata