Auxiliary Load (L0675)

Auxiliary Load is a 50.0 MW other interconnection project with a current status of active. It is proposed to connect at BPA's planned Manhattan Substation.

50.0 MWCapacity
ActiveStatus
Market
OtherTechnology

Project facts

Canonical nameAuxiliary Load
Queue IDL0675
Statusactive
Source statusSTUDY
Market
TechnologyOther
Capacity50.0 MW
State
County
Point of interconnectionBPA's planned Manhattan Substation
Requested (queue) date2025-12-03
Proposed in-service date2032-04-05
Operational date
Withdrawn date
DeveloperEnergy Efficiency Solar, Inc. dba ACRO Energy Inc.
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata