AZ Queue Project Q659 — Battery in Pinal, Arizona

AZ Queue Project Q659 — Battery in Pinal, Arizona is a 350.0 MW battery interconnection project in Pinal, Arizona with a current status of active. It is proposed to connect at Substation.

350.0 MWCapacity
ActiveStatus
AZMarket
BatteryTechnology

Project facts

Canonical nameAZ Queue Project Q659 — Battery in Pinal, Arizona
Queue IDQ659
Statusactive
Source statusDetected | Corrections Required Cluster Study Agreement
MarketAZ
TechnologyBattery
Capacity350.0 MW
StateArizona
CountyPinal
Point of interconnectionSubstation
Requested (queue) date2026-05-15
Proposed in-service date2032-06-29
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata