Bass Creek – Albany – North Monroe 138 kV (S1033)

Bass Creek – Albany – North Monroe 138 kV is a 25.0 MW generation interconnection project in Green, Wisconsin with a current status of operational. It is proposed to connect at Bass Creek – Albany – North Monroe 138 kV.

25.0 MWCapacity
OperationalStatus
Market
GenerationTechnology

Project facts

Canonical nameBass Creek – Albany – North Monroe 138 kV
Queue IDS1033
Statusoperational
Source statusActive
Market
TechnologyGeneration
Capacity25.0 MW
StateWisconsin
CountyGreen
Point of interconnectionBass Creek – Albany – North Monroe 138 kV
Requested (queue) date2022-08-15
Proposed in-service date2023-07-05
Operational date2023-07-05
Withdrawn date
Developer
Utility / transmission ownerAMERICAN TRANSMISSION COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata