Battery Storage (1091)
Battery Storage is a 50.4 MW battery interconnection project in Providence, Rhode Island with a current status of withdrawn. It is proposed to connect at The proposed POI is off the 115kV H17 transmission line owned by NEP via a spare buss position located in the Iron Mine HIll Substation owned by NEC..
50.4 MWCapacity
WithdrawnStatus
RIMarket
BatteryTechnology
Project facts
| Canonical name | Battery Storage |
|---|---|
| Queue ID | 1091 |
| Status | withdrawn |
| Source status | W |
| Market | RI |
| Technology | Battery |
| Capacity | 50.4 MW |
| State | Rhode Island |
| County | Providence |
| Point of interconnection | The proposed POI is off the 115kV H17 transmission line owned by NEP via a spare buss position located in the Iron Mine HIll Substation owned by NEC. |
| Requested (queue) date | 2021-01-14 |
| Proposed in-service date | 2022-05-02 |
| Operational date | — |
| Withdrawn date | 2021-11-01 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata