Battery Storage is a 200.0 MW battery interconnection project in Rockingham, New Hampshire with a current status of withdrawn. It is proposed to connect at Project will interconnect will be a shared facility at QP-1428's POI - via tap at existing 115 kV line between Eversource 115kV Scobie Pond - Pulpit Rock Line A184 115kV..

200.0 MWCapacity
WithdrawnStatus
NHMarket
BatteryTechnology

Project facts

Canonical nameBattery Storage
Queue ID1443
Statuswithdrawn
Source statusW
MarketNH
TechnologyBattery
Capacity200.0 MW
StateNew Hampshire
CountyRockingham
Point of interconnectionProject will interconnect will be a shared facility at QP-1428's POI - via tap at existing 115 kV line between Eversource 115kV Scobie Pond - Pulpit Rock Line A184 115kV.
Requested (queue) date2023-09-20
Proposed in-service date2026-12-30
Operational date
Withdrawn date2023-11-20
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata