Battle Creek - Island Road 138 kV Line (J2583)

Battle Creek - Island Road 138 kV Line is a 50.0 MW solar interconnection project in Eaton, Michigan with a current status of withdrawn. It is proposed to connect at Battle Creek - Island Road 138 kV Line.

50.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameBattle Creek - Island Road 138 kV Line
Queue IDJ2583
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity50.0 MW
StateMichigan
CountyEaton
Point of interconnectionBattle Creek - Island Road 138 kV Line
Requested (queue) date2022-09-14
Proposed in-service date2025-09-15
Operational date2025-09-15
Withdrawn date2025-08-01
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata