Belfair Substation (L0504)

Belfair Substation is a 38.3 MW other interconnection project in Mason, Washington with a current status of operational. It is proposed to connect at BPA's Shelton-Kitsap #2 115 kV line.

38.3 MWCapacity
OperationalStatus
WAMarket
OtherTechnology

Project facts

Canonical nameBelfair Substation
Queue IDL0504
Statusoperational
Source statusBPA COMPLETED
MarketWA
TechnologyOther
Capacity38.3 MW
StateWashington
CountyMason
Point of interconnectionBPA's Shelton-Kitsap #2 115 kV line
Requested (queue) date2021-09-29
Proposed in-service date
Operational date2023-09-27
Withdrawn date
DeveloperPublic Utility District No. 1 of Cowlitz County
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata