Bison 345kV Substation (GEN-2022-098)

Bison 345kV Substation is a 200.0 MW solar interconnection project in Johnston, Oklahoma with a current status of active. It is proposed to connect at Bison 345kV Substation.

200.0 MWCapacity
ActiveStatus
OKMarket
SolarTechnology

Project facts

Canonical nameBison 345kV Substation
Queue IDGEN-2022-098
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketOK
TechnologySolar
Capacity200.0 MW
StateOklahoma
CountyJohnston
Point of interconnectionBison 345kV Substation
Requested (queue) date2022-12-06
Proposed in-service date2029-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.