Bland 138 kV Substation (J2593)

Bland 138 kV Substation is a 140.0 MW solar interconnection project in Gasconade, Missouri with a current status of withdrawn. It is proposed to connect at Bland 138 kV Substation.

140.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameBland 138 kV Substation
Queue IDJ2593
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity140.0 MW
StateMissouri
CountyGasconade
Point of interconnectionBland 138 kV Substation
Requested (queue) date2022-09-14
Proposed in-service date2026-04-24
Operational date2026-04-24
Withdrawn date2026-10-20
Developer—
Utility / transmission ownerAmeren Missouri

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-05withdrawn_date—2026-10-20high
2026-11-05statusoperationalwithdrawnhigh
2026-10-31phasePhase 2Phase 3low
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.