Bluepoint Wind 1 (C24-021)

Bluepoint Wind 1 is a 1,310.0 MW wind interconnection project in Kings, New York with a current status of active. It is proposed to connect at Brooklyn Clean Energy Hub 345kV Substation.

1,310.0 MWCapacity
ActiveStatus
JMarket
WindTechnology

Project facts

Canonical nameBluepoint Wind 1
Queue IDC24-021
Statusactive
Source status6
MarketJ
TechnologyWind
Capacity1,310.0 MW
StateNew York
CountyKings
Point of interconnectionBrooklyn Clean Energy Hub 345kV Substation
Requested (queue) date2024-08-01
Proposed in-service date
Operational date
Withdrawn date
DeveloperBluepoint Wind LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata