Bluepoint Wind 2 (1611)

Bluepoint Wind 2 is a 1,310.0 MW wind interconnection project in Kings County, New York with a current status of withdrawn. It is proposed to connect at Gowanus 345 kV.

1,310.0 MWCapacity
WithdrawnStatus
JMarket
WindTechnology

Project facts

Canonical nameBluepoint Wind 2
Queue ID1611
Statuswithdrawn
Source status0
MarketJ
TechnologyWind
Capacity1,310.0 MW
StateNew York
CountyKings County
Point of interconnectionGowanus 345 kV
Requested (queue) date2023-09-26
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperBluepoint Wind LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata