Bluff Creek (Tap) to Sugar Creek 138 kV line tap (J892)

Bluff Creek (Tap) to Sugar Creek 138 kV line tap is a 75.0 MW solar interconnection project in Walworth County, Wisconsin with a current status of withdrawn. It is proposed to connect at Bluff Creek (Tap) to Sugar Creek 138 kV line tap.

75.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameBluff Creek (Tap) to Sugar Creek 138 kV line tap
Queue IDJ892
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity75.0 MW
StateWisconsin
CountyWalworth County
Point of interconnectionBluff Creek (Tap) to Sugar Creek 138 kV line tap
Requested (queue) date2017-06-16
Proposed in-service date2019-09-01
Operational date2019-09-01
Withdrawn date2018-03-12
Developer
Utility / transmission ownerAMERICAN TRANSMISSION COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata