Boyden - Sheldon 69kV line (J930)

Boyden - Sheldon 69kV line is a 38.0 MW wind interconnection project in Sioux County, Iowa with a current status of withdrawn. It is proposed to connect at Boyden - Sheldon 69kV line.

38.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameBoyden - Sheldon 69kV line
Queue IDJ930
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity38.0 MW
StateIowa
CountySioux County
Point of interconnectionBoyden - Sheldon 69kV line
Requested (queue) date2017-06-16
Proposed in-service date2019-09-15
Operational date2019-09-15
Withdrawn date2017-11-16
Developer
Utility / transmission ownerMIDAMERICAN ENERGY CO.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata