Brookfield Wind Energy (0425)
Brookfield Wind Energy is a 100.3 MW wind interconnection project in Chenango, Madison, New York with a current status of withdrawn. It is proposed to connect at Chadwicks - Yahnundadis 115kV.
100.3 MWCapacity
WithdrawnStatus
EMarket
WindTechnology
Project facts
| Canonical name | Brookfield Wind Energy |
|---|---|
| Queue ID | 0425 |
| Status | withdrawn |
| Source status | 0 |
| Market | E |
| Technology | Wind |
| Capacity | 100.3 MW |
| State | New York |
| County | Chenango, Madison |
| Point of interconnection | Chadwicks - Yahnundadis 115kV |
| Requested (queue) date | 2013-12-11 |
| Proposed in-service date | 2015-05-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Nextera |
| Utility / transmission owner | NM-NG |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.