Brookside Forest is a 300.0 MW battery interconnection project in Lowville, New York with a current status of active. It is proposed to connect at 115kV Waters Road Station.

300.0 MWCapacity
ActiveStatus
EMarket
BatteryTechnology

Project facts

Canonical nameBrookside Forest
Queue IDC26-0020
Statusactive
Source status1
MarketE
TechnologyBattery
Capacity300.0 MW
StateNew York
CountyLowville
Point of interconnection115kV Waters Road Station
Requested (queue) date2026-08-10
Proposed in-service date—
Operational date—
Withdrawn date—
DeveloperBrookside Forest Energy Storage LLC
Utility / transmission ownerNM-NG

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-12new_project—activehigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.