Brunner-West Hempfield 230kV (B31)

Brunner-West Hempfield 230kV is a 600.0 MW gas interconnection project in Lancaster, Pennsylvania with a current status of withdrawn.

600.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameBrunner-West Hempfield 230kV
Queue IDB31
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity600.0 MW
StatePennsylvania
CountyLancaster
Point of interconnection
Requested (queue) date1999-11-22
Proposed in-service date
Operational date
Withdrawn date2000-10-09
Developer
Utility / transmission ownerPPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata