BULLOCK - SAGINAW RIVER 138.0kV (J3816)

BULLOCK - SAGINAW RIVER 138.0kV is a 100.0 MW battery interconnection project in Saginaw, Michigan with a current status of withdrawn. It is proposed to connect at BULLOCK - SAGINAW RIVER 138.0kV.

100.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameBULLOCK - SAGINAW RIVER 138.0kV
Queue IDJ3816
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity100.0 MW
StateMichigan
CountySaginaw
Point of interconnectionBULLOCK - SAGINAW RIVER 138.0kV
Requested (queue) date2024-04-17
Proposed in-service date2028-06-01
Operational date2028-06-01
Withdrawn date2025-12-23
Developer—
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-24phaseStudy Not StartedPhase 2low
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.