CA5 - Palouse (CS23-06)
CA5 - Palouse is a 220.5 MW wind interconnection project in Whitman, Washington with a current status of active. It is proposed to connect at Shawnee - Thornton 230kV.
220.5 MWCapacity
ActiveStatus
WAMarket
WindTechnology
Project facts
| Canonical name | CA5 - Palouse |
|---|---|
| Queue ID | CS23-06 |
| Status | active |
| Source status | LGIA |
| Market | WA |
| Technology | Wind |
| Capacity | 220.5 MW |
| State | Washington |
| County | Whitman |
| Point of interconnection | Shawnee - Thornton 230kV |
| Requested (queue) date | 2023-04-14 |
| Proposed in-service date | 2025-12-15 |
| Operational date | — |
| Withdrawn date | — |
| Developer | CA5 - Palouse |
| Utility / transmission owner | Avista Utilities |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: avista-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata