CA8C - Othello is a 9.5 MW solar interconnection project in Adams, Washington with a current status of withdrawn. It is proposed to connect at Othello 13kV.
9.5 MWCapacity
WithdrawnStatus
WAMarket
SolarTechnology
Project facts
| Canonical name | CA8C - Othello |
|---|---|
| Queue ID | CS24-09 |
| Status | withdrawn |
| Source status | Withdrawn |
| Market | WA |
| Technology | Solar |
| Capacity | 9.5 MW |
| State | Washington |
| County | Adams |
| Point of interconnection | Othello 13kV |
| Requested (queue) date | 2024-04-29 |
| Proposed in-service date | 2025-08-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | CA8C - Othello |
| Utility / transmission owner | Avista Utilities |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: avista-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata