Cat Creek Energy, LLC (558)

Cat Creek Energy, LLC is a 120.0 MW solar interconnection project in Jerome, Idaho with a current status of active. It is proposed to connect at Hunt–Milner 138kV Line.

120.0 MWCapacity
ActiveStatus
IDMarket
SolarTechnology

Project facts

Canonical nameCat Creek Energy, LLC
Queue ID558
Statusactive
Source statusConstruction
MarketID
TechnologySolar
Capacity120.0 MW
StateIdaho
CountyJerome
Point of interconnectionHunt–Milner 138kV Line
Requested (queue) date2019-05-14
Proposed in-service date2023-10-31
Operational date
Withdrawn date
DeveloperCat Creek Energy, LLC
Utility / transmission ownerIdaho Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.