Chalk Point (G35)

Chalk Point is a 340.0 MW gas interconnection project in St. Mary's, Maryland with a current status of withdrawn.

340.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameChalk Point
Queue IDG35
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity340.0 MW
StateMaryland
CountySt. Mary's
Point of interconnection
Requested (queue) date2001-07-11
Proposed in-service date2004-12-01
Operational date
Withdrawn date2003-09-25
Developer
Utility / transmission ownerPEPCO

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata