Cherry Point Load (L0477)

Cherry Point Load is a 300.0 MW other interconnection project in Whatcom, Washington with a current status of withdrawn. It is proposed to connect at Either Custer 230 kV or Intalco 230 kV.

300.0 MWCapacity
WithdrawnStatus
WAMarket
OtherTechnology

Project facts

Canonical nameCherry Point Load
Queue IDL0477
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyOther
Capacity300.0 MW
StateWashington
CountyWhatcom
Point of interconnectionEither Custer 230 kV or Intalco 230 kV
Requested (queue) date2020-07-03
Proposed in-service date2024-07-06
Operational date
Withdrawn date
DeveloperPublic Utility District No. 1 of Cowlitz County
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.