Chestertown-Millington 69kV (Y3-033)

Chestertown-Millington 69kV is a 100.0 MW wind interconnection project in Kent, Maryland with a current status of withdrawn.

100.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameChestertown-Millington 69kV
Queue IDY3-033
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity100.0 MW
StateMaryland
CountyKent
Point of interconnection
Requested (queue) date2013-02-19
Proposed in-service date2018-04-30
Operational date
Withdrawn date2017-01-20
Developer
Utility / transmission ownerDPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.