Claremont Solar (676)

Claremont Solar is a 20.0 MW solar interconnection project in Sullivan, New Hampshire with a current status of withdrawn. It is proposed to connect at GMP 46 kV line 107 between High Bridge and Windsor.

20.0 MWCapacity
WithdrawnStatus
NHMarket
SolarTechnology

Project facts

Canonical nameClaremont Solar
Queue ID676
Statuswithdrawn
Source statusW
MarketNH
TechnologySolar
Capacity20.0 MW
StateNew Hampshire
CountySullivan
Point of interconnectionGMP 46 kV line 107 between High Bridge and Windsor
Requested (queue) date2017-08-03
Proposed in-service date2023-07-01
Operational date
Withdrawn date2021-10-05
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.