Clarion-Eagle Grove 69kV line (J939)

Clarion-Eagle Grove 69kV line is a 38.0 MW wind interconnection project in Wright County, Iowa with a current status of withdrawn. It is proposed to connect at Clarion-Eagle Grove 69kV line.

38.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameClarion-Eagle Grove 69kV line
Queue IDJ939
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity38.0 MW
StateIowa
CountyWright County
Point of interconnectionClarion-Eagle Grove 69kV line
Requested (queue) date2017-06-16
Proposed in-service date2019-09-15
Operational date2019-09-15
Withdrawn date2018-10-12
Developer
Utility / transmission ownerMIDAMERICAN ENERGY CO.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.