Clark County-Ironwood 345kV (GEN-2016-046)

Clark County-Ironwood 345kV is a 297.6 MW wind interconnection project in Ford County, Kansas with a current status of operational. It is proposed to connect at Clark County-Ironwood 345kV.

297.6 MWCapacity
OperationalStatus
KSMarket
WindTechnology

Project facts

Canonical nameClark County-Ironwood 345kV
Queue IDGEN-2016-046
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketKS
TechnologyWind
Capacity297.6 MW
StateKansas
CountyFord County
Point of interconnectionClark County-Ironwood 345kV
Requested (queue) date2016-03-31
Proposed in-service date
Operational date2018-12-01
Withdrawn date
Developer
Utility / transmission ownerSUNC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-07capacity_mw299.0297.6high
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.