Clark County-Ironwood 345kV (GEN-2026-SR28)

Clark County-Ironwood 345kV is a 297.6 MW battery interconnection project in Dodge City, Kansas with a current status of active. It is proposed to connect at Clark County-Ironwood 345kV.

297.6 MWCapacity
ActiveStatus
KSMarket
BatteryTechnology

Project facts

Canonical nameClark County-Ironwood 345kV
Queue IDGEN-2026-SR28
Statusactive
Source statusSPECIAL STUDY
MarketKS
TechnologyBattery
Capacity297.6 MW
StateKansas
CountyDodge City
Point of interconnectionClark County-Ironwood 345kV
Requested (queue) date2026-06-04
Proposed in-service date2029-01-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerSUNC

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.