Clarksville 345kV Substation (GEN-2017-170)

Clarksville 345kV Substation is a 52.0 MW battery interconnection project in Wagoner, Oklahoma with a current status of withdrawn. It is proposed to connect at Clarksville 345kV Substation.

52.0 MWCapacity
WithdrawnStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameClarksville 345kV Substation
Queue IDGEN-2017-170
Statuswithdrawn
Source statusWITHDRAWN
MarketOK
TechnologyBattery
Capacity52.0 MW
StateOklahoma
CountyWagoner
Point of interconnectionClarksville 345kV Substation
Requested (queue) date2017-11-29
Proposed in-service date
Operational date
Withdrawn date2018-12-27
Developer
Utility / transmission ownerSPP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.