CMP Winslow 115 kV SS - Winslow-Lakewood Areas Study (1096)
CMP Winslow 115 kV SS - Winslow-Lakewood Areas Study is a 18.7 MW solar+battery interconnection project in Somerset/Kennebec, Maine with a current status of withdrawn. It is proposed to connect at CMP Winslow 115 kV SS.
18.7 MWCapacity
WithdrawnStatus
MEMarket
Solar+BatteryTechnology
Project facts
| Canonical name | CMP Winslow 115 kV SS - Winslow-Lakewood Areas Study |
|---|---|
| Queue ID | 1096 |
| Status | withdrawn |
| Source status | W |
| Market | ME |
| Technology | Solar+Battery |
| Capacity | 18.7 MW |
| State | Maine |
| County | Somerset/Kennebec |
| Point of interconnection | CMP Winslow 115 kV SS |
| Requested (queue) date | 2021-02-04 |
| Proposed in-service date | 2024-04-30 |
| Operational date | — |
| Withdrawn date | 2025-06-13 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.