CO100SB Project (LG-19-3-4)

CO100SB Project is a 100.0 MW solar+battery interconnection project in Otero County, New Mexico with a current status of active. It is proposed to connect at Escondido 115 kV Substation.

100.0 MWCapacity
ActiveStatus
NMMarket
Solar+BatteryTechnology

Project facts

Canonical nameCO100SB Project
Queue IDLG-19-3-4
Statusactive
Source statusLGIA EXECUTED
MarketNM
TechnologySolar+Battery
Capacity100.0 MW
StateNew Mexico
CountyOtero County
Point of interconnectionEscondido 115 kV Substation
Requested (queue) date2019-03-27
Proposed in-service date2027-04-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerEl Paso Electric Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: epe-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.